Check these four items before analyzing your budget numbers

By Tom Mochal, PMP, TSPM, ITBMC

BudgetProject managers need to manage schedule and costs on their project. The sponsor has agreed to pay a certain amount of money for a certain solution. If the solution ends up costing more than anticipated, the solution may or may not be viable from a business perspective.

Managing the budget is vastly different from company to company. In my experience of teaching and consulting in organizations around the world, many organizations (perhaps most) treat the budget as an abstract concept since they use internal resources for projects and they do not have the accounting systems to track and report costs allocated to a specific project.

Let’s assume that you work in an organization where you are held accountable for delivering within the project budget and you have the accounting information you need. You want to be in a position to know very quickly if you are trending over your budget. Before you can do the proper budget analysis you have to factor in a number of items.

· Monthly spending. You rarely spend money at a constant rate. You cannot just take a 12 month project budget and divide it into 12 equal installments. You need to first understand what you expected to spend during each month, as well as what you actually spent. This information is vital to make sure that you can make the proper budget analysis.

· Reporting lag. In most companies, updated financial information is only available monthly and with an additional reporting lag. For instance, you might not know the financial status of your project for the current month until the second week of the following month when the budget reports are released. Some of the spending information may be up to six weeks old by that time. You should keep track of your large expenditures on a weekly basis to make sure there are no large surprises when you receive the budget reports.

· Expense timing. You need to know when your company recognizes expenses. Your company might recognize an expenses when you receive an invoice, or perhaps not until you pay an invoice, which may be much later. If your company uses purchase orders, your project may get hit with a project charge when the purchase order is generated, even if the actual invoice is not paid for weeks later. This may cause expenses to hit early and may make it appear that you are trending overbudget, when really you are not. The expenses are just hitting your budget earlier than you had planned.

· Misallocations. It is common that expenses can get misallocated from one project to another. One of your first activities after you receive the latest budget numbers is to validate that the details are correct. This requires the project manager (or a designee) to review each line item. You could have great accounting software, but if someone enters an incorrect project code, you may get charged for the expenses from someone else’s project. If the project manager finds a potential problem, the matter can be brought to the attention of an accounting resource for correction. Of course, there are times when your project expenses may end up on someone else’s project as well. You need to recognize this. Otherwise, you may get hit for an “unexpected” expense months later when the other project manager catches the error.

As a project manager, you must understand these four budget items. If you do not recognize and understand them it is possible (even likely) that you will not properly understand your budget status and you may make wrong decisions based on these misunderstanding.

Published by Josh Nankivel with permission from the author
————————————————
TomMochalTom Mochal, PMP, TSPM, ITBMC
President, TenStep, Inc.
Winner of the Distinguished Contribution Award from PMI
770.795.9097
TenStep. You can manage
Share

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top